The Project was awareded by respected Zabul Provincial Reconstruction Team (PRT) and DWCC completed this project with high quality, DWCC applied high standards of Construction Norms and Methods to complete the project.
The Gabion Wall Construction is in progress by the workers of DWCC.
The Gabion Wall Construction is in Progress by the workers of DWCC
Back filling of gabion wall is in progress by DWCC machinery
The retaining wall constructed by DWCC during the implementation of Shado Canal Project
Gabion wall constructed by DWCC during the implementation of the Shado Canal Project
Completed view of the canal opening
Completed View of a wash constructed by DWCC
Completed View of Retaining Wall constructed by DWCC
Completed View of Retaining wall constructed by DWCC, The project got successfully completed in 2011