Tuesday, May 3, 2016

Construction of 240 meters boundary wall of Qalat Slaughter House in Qalat city of Zabul Province. The Project was awarded by respective Chemonics RAMP-UP South/USAID in 2013

Project Site leveling is in progress by DWCC machinery 

Excavation of foundation is in progress by DWCC labors

Compaction of Foundation is in progress by DWCC labors

Foundation Picture

A view of Brick Masonry done by DWCC 

Completed view of the project

Purchasing and Installation of Networking system for Crisis Management Center (CMC) in Governor Compound of Ghazni. The Project was awarded by respective Polish PRT of Ghazni in August 2013 and DWCC completed the project in October 2013


Installation of Network is in progress, All the equipment were delivered and installed by DWCC

A view of main control room, All equipment were delivered and installed by DWCC

DWCC organized a training for government officials in order to show them how to use the equipment

Construction of 2 MRRD Food Warehouses in Qalat city of Zabul Province. The Project was awarded by the respective Zabul PRT (US) in September 2012 and DWCC completed the project successfully by applying high standards of construction in February 2013


                                                  Project Site Preparation is in progress 



Construction of Columns are in progress by DWCC staff

High standard of column construction was used by DWCC

The Painting of Warehouse is progress by DWCC painters

Final View of Constructed Warehouses by DWCC











Sunday, August 26, 2012

Construction of Five Agriculture Collection Centers in Four District and Qalat City of Zabul Province 2011

This Project was awarded by respected Zabul Agri-business Development Team (ADT) and DWCC completed the project with high quality on time with scheduale

Completed View of Qalat Collection Center Constructed by DWCC in 2011


Completed View of Tarnak Wa Jaldak District Collection Center Constructed by DWCC in 2011


Completed View of Mizan District Collection Center Constructed by DWCC in 2011


Completed View of Shahjoy District Collection Center Constructed by DWCC in 2011




View of DWCC logo painted on each facility

Shado Canal Renovation Project in Qalat City of Zabul Province 2010

 The Project was awareded by respected Zabul Provincial Reconstruction Team (PRT) and DWCC completed this project with high quality, DWCC applied high standards of Construction Norms and Methods to complete the project.

The Gabion Wall Construction is in progress by the workers of DWCC.


The Gabion Wall Construction is in Progress by the workers of DWCC

Back filling of gabion wall is in progress by DWCC machinery


The retaining wall constructed by DWCC during the implementation of Shado Canal Project


Gabion wall constructed by DWCC during the implementation of the Shado Canal Project


Completed view of the canal opening


Completed View of a wash constructed by DWCC


Completed View of Retaining Wall constructed by DWCC


Completed View of Retaining wall constructed by DWCC, The project got successfully completed in 2011

Sunday, August 14, 2011

Renovation of 6 Kilometers of Mirza Gul Mohammad Canal Project in Qalat City of Zabul Province 2011

The Mirza Gul Mohammad 6 Kilometers Canal Renovation Project was awarded by respected Zabul PRT in 2010 and DWCC Compelted this project with high quality in 2011 and received a project completion certificate as well.

DWCC Machinery is excavating the foundation for Flood Protection wall in Mirza Gul Mohammad Canal 2010


DWCC Workers are working on Flood Protection Wall construction in Mirza Gul Mohammad Canal 2010



Work on Flood Protection Wall construction in Mirza Gul Mohammad Canal is in progress 2010


The Completed View of Flood Protection Wall construction in Mirza Gul Mohammad Canal 2010

The Completed View of Flood Protection Wall construction in Mirza Gul Mohammad Canal 2010

The Completed View of Water Entrance to Mirza Gul Mohammad Canal 2010

The Construction of Gabbion Wall is in progress in Mirza Gul Mohammad Canal 2011


The Completed view of Gabbion Wall in Mirza Gul Mohammad Canal 2011


Mirza Gul Mohmmad Canal Opening Ceremony (Zabul Provincial Governor Mr. Mohammad Ashraf "Nasiri" is cutting the ribbin) 2011

Monday, June 20, 2011

Construction of Road in Bazaar of Moqur District of Ghazni Province 2009

DWCC completed the Construciton of 680 Cobble Stone Road Project in Bazaar of Moqur District of Ghazni Province. The project was awarded by Respected Ghazni Polish PRT. DWCC completed this project in 2009.

Machinery of DWCC is Granding the Kabul Kandahar road shoulder


Machinery of DWCC is Granding the Kabul Kandahar road shoulder

DWCC workers are paving the cobble stone on Kabul Kandahar Road Shoulders in Moqur District Bazaar in Ghazni Province.

The Completed View of Kabul Kandahar Highway 1 Shoulder in Moqur District Bazaar of Ghazni Province the project has been implemented by DWCC.

The Completed View of Kabul Kandahar Highway 1 Shoulder in Moqur District Bazaar of Ghazni Province the project has been implemented by DWCC.


The Graded View of District Center Road from Kabul-Kandahar Highway 1 to District Center (Grading has been done by DWCC).

DWCC Workers are Paving the Cobble Stone on Kabul-Kandahar Highway 1 to District Center Road


 Completed view of Project, The Project has been completed with a high quality in 2009 by DWCC with Financial Support of Respected Ghazni Polish PRT